Norway halts new data centre grid reservations and plans licences for the centres it needs
Statnett stopped taking new grid capacity reservations for data centres on Monday, Nov. 9, while the Government set out a licensing scheme for existing and future centres, with crypto operations ruled out as socially beneficial and priority promised to the consumption society needs in order to function.
OSLO: Norway's transmission system operator Statnett has temporarily stopped new grid capacity reservations for data centres, in a decision announced on Monday, Nov. 9, on the same morning the Government set out plans for a licensing scheme covering the establishment and operation of data centres in Norway.
Statnett said the halt covers new connection reservations and the processing of new applications for approval of facility functionality under section 14 of the system responsibility regulation. It also covers applications already received for facilities that would connect directly to the 420 kV network. The measures apply to large withdrawal customers with a distinctive load profile, typically data centres, the operator said.

The scale behind the decision is set out in both releases. Data centres with a combined load of 800 megawatts (MW) are connected to the grid, 4,200 MW have reserved capacity and 9,100 MW are waiting in the capacity queue, with requests on file for a further 18,000 MW. By comparison, Norway's maximum power consumption is slightly over 25,000 MW, Statnett and the Government said.
A pause for technical rules, not a general stop
Statnett said the halt is a risk reducing measure for the power system, taken while the knowledge base for future requirements is built. Data centres differ from traditional large power consumption, the operator said, because they can show large and rapid changes in load, software controlled load, and a higher vulnerability to disturbances in the power system.
The halt is expected to be lifted by Aug. 1, 2027 at the latest, and it lasts until Statnett has developed and set the necessary functional requirements for data centre facilities and those requirements have been approved by RME, the Norwegian Energy Regulatory Authority, alongside effective mechanisms to secure compliance. The requirements Statnett prepares will be sent out for consultation and must be approved by RME, and Statnett said it will look to corresponding requirements at the other Nordic system operators and at ENTSO-E, the European association of transmission system operators.

Examples the operator gave of the requirements under preparation include rules on the situations in which data centres must not disconnect from the grid during operating disturbances, rules on how fast consumption in a data centre may change, and technical requirements that can reduce the risk of a data centre causing oscillations in the network. Statnett stressed that its decision is not a general halt to connecting data centres: facilities that have had the necessary functional requirements approved can still connect, and existing connections are not affected. Applications already received for facilities in the regional grid with commissioning planned in the near future will not be stopped, and Statnett said available capacity will not be allocated to other customers where that would come at the expense of data centres ahead of them in the queue.
Licences for existing and future centres
The Government said it will work for controlled growth of data centres in Norway and for centres that are as socially beneficial as possible, and that it aims to introduce a licensing scheme for existing and future data centres, with robust transitional arrangements. It said other forms of regulation will also be assessed, and that it will return with the main principles for the scheme.
Under the scheme as set out on Monday, requirements and conditions that support digital security and preparedness, and that contribute to necessary AI computing capacity in Norway, the Nordic region and Europe, will be assessed. Data centres carrying on crypto operations will not be regarded as socially beneficial, the Government said. Digitalisation and Public Governance Minister Torgeir Micaelsen said data centres are part of Norway's critical infrastructure and contribute to value creation, safe digital services and greater digital independence, but that Norway does not want every type of data centre and needs the ones that contribute the most societal benefit.
The wider package includes quick regulatory changes by the Ministry of Energy so that Statnett can set the necessary conditions for safe connection, a priority for consumption that society needs in order to function, a modernised connection obligation for grid companies, and a requirement that large new power consumption contribute more towards the costs of building new grid and the costs it imposes on system operation. The Government said it will talk with the data centre industry about how the industry itself, on a commercial basis, can help build the power production needed to make larger facilities possible sooner, including gas power plants with carbon capture and storage and offshore wind, and that it will assess models for state ownership in particularly socially beneficial data centre projects.
Energy Minister Terje Aasland said the Government is facilitating more and faster development of power and grid, but that it is neither desirable nor possible to build enough to cover the power demand coming from data centres wanting to establish themselves in Norway, and that Norway must have enough power in the right place for socially beneficial purposes.